110.41Inspections and Tests

Article 110GENERAL REQUIREMENTS FOR ELECTRICAL INSTALLATIONS

NEC 110.41 - Inspections and Tests: The "Show Your Work" Rule

The Old Foreman's Translation

Alright, listen up. You know how your third-grade teacher made you show your work on math tests? Well, the NEC just turned into Mrs. Henderson, except now we're talking about gear that can vaporize you instead of long division.

Here's the deal: Before you flip that switch on a new electrical system, you better have your ducks in a row—and paperwork to prove it.

Part (A): The "Trust But Verify" Clause

When the Code says you need testing "where required elsewhere" (spoiler: it's required A LOT for bigger installations), you can't just wire it up, say a prayer, and slap the breaker closed. Nope. You need:

  1. A complete electrical system design – Not scribbled on a McDonald's napkin, either. We're talking actual documentation.

  2. All your settings documented – Every protective relay, every breaker trip setting, every control circuit parameter. If it switches, protects, or controls something, write it down.

  3. Available ON REQUEST – That means the AHJ (inspector) doesn't have to beg, threaten, or file a Freedom of Information Act request. When they ask, you hand it over with a smile.

  4. Actually TEST the damn thing – Installation day is test day. Megger those cables, check your phase rotation, verify your ground fault settings actually work. This ain't a "trust me, bro" situation.

Think of this like a flight checklist. Pilots don't just eyeball the instrument panel and say "looks good!" They run through the checklist every single time because gravity doesn't care about your feelings—and electricity doesn't either.

Part (B): The Paper Trail That Might Save Your Bacon

Now you've done all your testing (good for you!), but here's the kicker: You need a written report. And not just for you to stick in a drawer somewhere while it collects dust next to your 1987 Snap-on calendar.

This test report must be:

  • Available to the AHJ BEFORE you energize – That's BEFORE, not "during," not "after the smoke clears," but BEFORE. The inspector needs to see that you actually tested stuff and it passed.

  • Available to everyone who needs it – Installers (that's you), operators (facility guys), maintenance people (poor souls), and testers (the nerds with the fancy meters). Basically, anyone who might touch this system needs access to this report.

Why? Because six months from now when something trips offline at 2 AM, the maintenance guy shouldn't have to play detective trying to figure out if that relay is SUPPOSED to trip at 600 amps or if something's wrong. The answer should be in the report you're holding right now.


Key Takeaways (The Stuff That Actually Matters)

🔧 System design and settings must be documented in advance – No winging it on installation day

🔧 Testing is required on first installation – Initial startup isn't just "flip and pray"

🔧 Test reports must be available to the AHJ BEFORE energization – They approve, THEN you power up

🔧 Reports must stay available to anyone who installs, operates, tests, or maintains the system – Think of it as the system's permanent record

🔧 This applies "where required elsewhere in the Code" – Check other sections for when testing is mandatory (hint: most commercial/industrial systems)


Real-World Scenarios (Tales From the Trenches)

Scenario 1: The "It'll Be Fine" Disaster

Johnny Sparks gets hired to install a new 2000A service with a fancy microprocessor-based trip unit for a manufacturing plant. He's done a hundred of these. He sets the breaker trips "like he always does," fires it up, and heads home feeling like a champion.

Three weeks later, a minor ground fault takes down the entire plant. Turns out Johnny set the ground fault pickup at 1200A when the engineer's coordination study called for 400A. The inspector never reviewed any test reports (there weren't any), and now lawyers are circling like vultures at a roadside barbecue.

The lesson? Document your settings, test them, and get approval. That paper trail is cheaper than a lawyer.

Scenario 2: The Midnight Emergency

It's 2 AM. Something's wrong with the emergency generator transfer switch at the hospital. The maintenance guy is frantically trying to figure out if the 5-second delay is correct or if the switch is malfunctioning. He's searching through emails, calling the electrician (who isn't answering), and sweating bullets because patients are on life support.

If only someone had followed 110.41(B) and left a proper test report showing that yes, 5 seconds IS the correct delay setting as tested during installation.

The lesson? Your test report isn't just paperwork—it's a troubleshooting bible for the next guy.

Scenario 3: The Inspector Who Wouldn't Leave

Big commercial project, final inspection day. The inspector asks for your test reports on the 480V distribution system. You hem and haw. He crosses his arms. You admit you "tested everything" but didn't write it down. He smiles—not a friendly smile—and says "No report, no approval. See you next week."

Now you're explaining to the GC why the project got delayed, and the GC is explaining to you why you're not getting paid until this is resolved.

The lesson? The inspector isn't being a jerk—they're literally following 110.41. Beat them to the punch with proper documentation.


What to Study (Exam Survival Guide)

If you're taking your journeyman or master's exam, here's what the test writers LOVE about 110.41:

High-Probability Test Questions:

  1. WHEN must test reports be available?

    • Answer: BEFORE energization (not after, not during, BEFORE)
  2. WHO must have access to test reports?

    • Answer: AHJ + anyone who installs, operates, tests, or maintains the system
  3. What documentation is required for protective devices?

    • Answer: Settings for protective, switching, and control circuits
  4. When must testing occur?

    • Answer: When FIRST installed on-site (initial installation)

Common Exam Traps:

❌ "Test reports must be available within 30 days" – WRONG. It's BEFORE energization, no grace period.

❌ "Only the AHJ needs access to reports" – WRONG. Multiple parties need access.

❌ "Testing can be done after energization if supervised" – WRONG. Test BEFORE you energize.

Memory Trick:

"Test Before Touch, Document For Everyone"

  • Test = Required on initial installation
  • Before = Reports due BEFORE energization
  • Touch = Energize
  • Document = Written reports required
  • Everyone = AHJ plus all the maintenance folks

The Bottom Line

Look, nobody got into electrical work because they love paperwork. We all became electricians because we like building stuff, solving puzzles, and occasionally making sparks fly (preferably on purpose).

But here's the thing: 110.41 exists because people died. Someone, somewhere, energized a system that wasn't properly tested or documented, and bad things happened. This section is written in blood, just like most of the Code.

So yeah, it's a pain to document everything and write test reports. But it's way less painful than explaining to OSHA, your insurance company, or a jury why you didn't bother.

Do the tests. Write the reports. Keep everyone in the loop. Your future self—and possibly your lawyer—will thank you.

Now get back to work. Those cables aren't gonna pull themselves. 🔌⚡


Remember: The Code is minimum standards. If your company or project specs require MORE documentation or testing, do that too. When in doubt, over-document. Paper is cheap; lawsuits aren't.

NEC Reference: Section 110.41 · 2026 NEC (NFPA 70)